This Report is a SUMMARY BY JOB of CONTRACT, ESTIMATE, COST-TO-DATE and BILLINGS.
PERCENT COMPLETE is derived from Estimate and Cost (% of Budget spent)
Cost Over & Under-Run can be posted using Step 1 on the Menu, to ALTER this Percent
Complete to reflect % of WORK COMPLETED.
Over and Under Billings are computed based on AMOUNT BILLED-TO-DATE and PERCENT
COMPLETE. You have an Option to POST THE NET TOTAL OVER/UNDER BILLED as a
Journal Entry to the General Ledger to ADJUST SALES.
--------------------------------------------------------------------------------------------------------------------------------------
After the Job Code and Job Description are printed, the below listed Amounts are printed
across the page:
Contract Price Estimated Costs Billed to Date Costs to Date
PERCENT COMPLETE COST OVER/UNDER RUN FLAG
COST TO COMPLETE OVER / UNDER BILLED EARNED TO DATE